Rooftop Unit Start-Up: Three-Phase Voltage, Compressor Rotation and the Checks That Matter

Light commercial rooftop units add a few things a residential split system doesn't have: three-phase power, scroll compressors that can run backward, an economizer, and often gas heat in the same cabinet. The start-up checks that matter most go with those.

This guide follows Carrier's installation and service instructions for its current 48FE and 50FE rooftop units. Other brands use the same checks with their own numbers, so the unit's own manual and nameplate come first.

Before power goes on

Carrier's pre-start inspection:

  • Remove all access panels and read the labels on the unit.
  • Look for shipping damage: broken lines, loose parts, disconnected wires.
  • Look for oil at refrigerant connections and on the base. Oil generally means a refrigerant leak, so leak-test the connections.
  • Check that factory and field wiring connections are complete and tight, and that no wire is rubbing on tubing or a sharp edge.
  • Straighten any bent coil fins with a fin comb.
  • Confirm filters are in, outdoor air inlet screens are in place, the condenser fan blade sits correctly in its orifice, and no tools or loose parts are left in the unit.
  • Fill the condensate trap with water. A dry trap won't drain properly.

Carrier's start-up checklist adds: packaging removed, outdoor air hood installed, unit level, the supply fan free of obstructions and spinning freely, ground continuity verified, and crankcase heaters energized for at least 24 hours before the compressors run. That last one has to be planned, since power must be on the day before.

Don't loosen the compressor hold-down bolts. On these units the compressors are spring-mounted internally and the bolts stay tight.

Condensate trap

Carrier requires an external trap on every unit:

  • At least 4 inches deep, and protected from freezing.
  • Any drain line run after the trap pitched away from the unit at 1 inch per 10 feet.
  • Pipe no smaller than the unit's 3/4 inch connection.

Carrier's note on the drawing gives the reason: the trap has to be deep enough to offset the unit's maximum static pressure difference.

Supply voltage and phase balance

Measure voltage between each pair of legs: L1 to L2, L2 to L3 and L1 to L3. Two things have to be true:

  1. The voltage is within the range on the unit nameplate at the compressor terminals while it's running.
  2. The three readings are balanced within 2%, and the current on the three legs within 10%.

The formula from Carrier's instructions:

% voltage imbalance = 100 × (largest deviation from average voltage) ÷ average voltage

Carrier's example, on a 230-volt three-phase supply:

Reading Volts Deviation from 227 V average
A to B 224 3
B to C 231 4
A to C 226 1

The largest deviation is 4 volts. 100 × 4 ÷ 227 = 1.76%, which is under the 2% limit.

Use the three-phase voltage imbalance calculator to run your own readings. It also checks current balance against the 10% limit.

If the supply is more than 2% out of balance, Carrier's instruction is to contact the electric utility. Don't leave the unit running on it: Carrier states that operating on improper line voltage or excessive phase imbalance is abuse that can damage electrical components and void the warranty.

208-volt supplies

Units other than 208/230-volt models are factory wired for the nameplate voltage. A 208/230-volt unit is shipped wired for 230. If the building supply is 208 volts, move the control transformer's primary lead from the 230-volt terminal to the 208-volt terminal (Carrier labels it 200-v), following the unit's wiring diagram. Leave it on the 230 tap with a 208 supply and the control voltage runs low.

Compressor rotation

A scroll compressor only pumps in one direction. On three-phase power, direction depends on phase sequence, so a newly connected unit can run backward the first time it starts. Carrier's caution is direct: running in reverse for extended periods can damage the compressor internally, and a scroll is a sealed unit that can't be repaired on site.

Carrier's check:

  1. Connect service gauges to the suction and discharge ports.
  2. Energize the compressor.
  3. Suction pressure should drop and discharge pressure should rise, as on any normal start.

If the pressures don't move that way:

  1. Note that the supply fan is probably running backward too.
  2. Shut off power to the unit and lock it out.
  3. Reverse any two of the unit's power leads.
  4. Re-energize and check the pressures again.

A compressor running backward is also noticeably louder than normal and doesn't cool.

Carrier's instruction is to swap the unit's power leads, not the leads at the compressor, which corrects the compressor and the fan together. A phase monitor is a factory option on these units, but the gauge check is still the proof.

Cooling check

  • Set the thermostat to cool with the fan on auto and the setpoint below room temperature. The compressor starts when the contactor closes.
  • Check charge using the charging chart for the unit. On these Carrier units that means a pressure gauge on the discharge port and a temperature sensor strapped to the liquid line and insulated, with indoor airflow in its normal range. Each manufacturer's method and chart is different, so use the one printed for the unit.
  • Raise the setpoint and confirm the compressor shuts off.

Record amps on all three legs for each compressor and for the supply fan, and compare them with the nameplate.

Gas heat check

  • Check the gas piping for leaks.
  • Pressure testing the gas line: above 0.5 psig, the unit must be disconnected from the piping. At 0.5 psig or less, the unit's manual gas valve must be closed to isolate it. Carrier's warning is that a gas valve exposed to more than 0.5 psig must be replaced before use.
  • Purge air from the gas line before lighting.
  • Confirm the burners light and the supply fan comes on, then confirm they shut down when the call is removed.
  • If the burners don't light or lock out, read the IGC board's LED before cutting power, since a power interruption erases the code. See the Carrier 48FE IGC flash codes.
  • Measure inlet and manifold gas pressure and the temperature rise, and compare them with the unit's data. Adjust airflow to bring the temperature rise into the nameplate range. See temperature rise for the airflow math.

R-454B units: the dissipation board

Rooftop units charged with R-454B have a leak dissipation system that runs the indoor fan if refrigerant is detected. Carrier's checklist has two items for it:

  • The yellow status LED on the dissipation board is steady.
  • Pressing the board's test button runs the indoor fan for one minute.

Economizer and controls

  • Set the economizer's minimum ventilation position and its changeover setting, and write both on the start-up sheet. See economizer setup and troubleshooting for the defaults and the built-in test commands.
  • On units with direct digital controls, use the controller's service test function to step through the outputs, and configure it for whatever accessories were field-installed.
  • Test the smoke detector shutdown if the unit has one.

What to write down

Carrier's start-up checklist records, and so should yours:

Reading Where
Supply voltage L1-L2, L2-L3, L3-L1
Voltage to ground Each leg
Compressor amps All three legs, each compressor
Supply fan amps All three legs
Air temperatures Outdoor dry bulb, return dry bulb and wet bulb, supply air in cooling and in heating
Refrigerant pressures Suction and discharge, each circuit
Gas pressures Inlet and manifold, each stage
Economizer Minimum position and changeover settings

Leave a copy with the job file. It's the baseline for every later service call. For the residential version of this process, see HVAC commissioning measurements and tolerances.

After start-up

Carrier's service manual sets the first maintenance visit at 30 days after start-up, then quarterly: replace return air filters, clean the outdoor air hood filters, check the condenser coil and check the condensate drain. The rooftop unit maintenance checklist has those items plus the seasonal ones, with spaces for readings. On belt-drive units, see belt tension and pulley alignment; the 48FE 20-30 units covered here use a direct-drive fan with no belt.

Quick reference

Check Value Source
Voltage imbalance between phases 2% maximum Carrier 50FE installation instructions
Current imbalance 10% maximum Carrier 50FE installation instructions
Condensate trap depth 4 in. minimum Carrier 50FE installation instructions
Drain line pitch after trap 1 in. per 10 ft Carrier 50FE installation instructions
Crankcase heater before start 24 hours minimum Carrier 48FE start-up checklist
Gas valve maximum test pressure 0.5 psig Carrier 48FE service instructions
Wrong compressor rotation Reverse any two unit power leads Carrier 48FE service instructions

Sources

  • Carrier, 50FE 08-14 Installation Instructions (condensate trap, field power supply and voltage imbalance, pages 16-18): shareddocs.com
  • Carrier, 48FE 20-30 Service and Maintenance Instructions (pre-start-up and start-up, pages 83-86, and the start-up checklist): shareddocs.com