HVAC Commissioning: The Measurements and Tolerances That Prove an Install
A system that starts and blows cold air has not been commissioned. Commissioning is measuring the handful of things that decide capacity, efficiency and equipment life, comparing them with the design and the manufacturer's data, and writing the numbers down.
This guide follows ENERGY STAR's National HVAC Commissioning Checklist and ENERGY STAR's summaries of ACCA Standard 5 (HVAC Quality Installation Specification). The manufacturer's installation instructions always come first for the unit in front of you.
What a quality install comes down to
ENERGY STAR's quality installation guide lists proper equipment sizing and component matching, correct refrigerant charge, and enough airflow to match the refrigerant capacity among its main components, and its savings table adds duct sealing. Its estimate of the savings from getting each right: refrigerant charge 2-6%, airflow 2-5%, sizing 3-7%, and duct sealing 11-18%.
1. Airflow
Check airflow first: charge readings aren't reliable until airflow is right.
- Target: measured fan airflow within ±15% of design, and within the range in the manufacturer's product data.
- Measure it, don't calculate it. ENERGY STAR's accepted methods: pressure matching, a flow grid, a traverse with a manometer and probe or an anemometer, the manufacturer's CFM-versus-static-pressure table, or temperature rise (furnaces only).
- Static pressure: drill and mark test holes, measure total external static pressure, and compare it with the design value. ENERGY STAR's quality installation program allowed no more than 25% or 0.10 in. w.c. (whichever is greater) over the design static, and always within the manufacturer's range.
The usual field method is static pressure plus the blower table: read total external static, find the fan speed setting, and read CFM from the manufacturer's chart. See residential duct design basics if static is over the rating.
2. Refrigerant charge
- Run the system 15 minutes before taking readings.
- TXV systems: use subcooling. Liquid saturation temperature minus liquid line temperature should be within ±3°F of the manufacturer's subcooling target.
- Fixed orifice (piston) systems: use superheat. Suction line temperature minus evaporator saturation temperature should be within ±5°F of the manufacturer's target for the indoor and outdoor conditions.
- Cold weather: if it's below 55°F at the condenser (or below the manufacturer's minimum for cooling), the checklist doesn't use these tests. It requires the system to have a TXV, has you record the outdoor temperature, and marks the charge section N/A. Follow the manufacturer's cold-weather charging instructions.
- Manufacturer method wins. Where the manufacturer defines its own test procedure, use it and attach it.
Record all of it: outdoor and return air temperatures, liquid and suction pressures, both line temperatures, the target and the difference. See superheat vs. subcooling and the superheat and subcooling calculator.
Before charge can be right, the line set has to be clean, tight and dry: nitrogen purge while brazing, a pressure test, and a deep vacuum.
3. Electrical
ACCA 5's installation elements include voltage, amperage and grounding. Measure supply voltage at the unit with it running and compare amp draws with the nameplate.
4. Gas furnaces: input and temperature rise
ACCA 5's fuel-fired checks, as ENERGY STAR summarizes them:
- Firing rate (on-rate): within 5% of nameplate input. Clock the meter or measure manifold pressure per the manufacturer; see furnace gas pressure check.
- Temperature rise: within the range on the rating plate; see furnace temperature rise.
- Venting: per code and the installation instructions.
- Combustion analysis where the manufacturer calls for it.
5. Ducts and room airflow
- Duct leakage (ACCA 5, per ENERGY STAR's summary): new ducts inside conditioned space, 10% total leakage or less; ducts outside the thermal envelope, 6% or less. For existing ducts, 20% or less, or a 50% reduction from where they started.
- Room-by-room balance (recommended on the ENERGY STAR checklist, not required): each room's measured airflow within the greater of ±20% or 25 CFM of design.
6. Controls and paperwork
- Check that the thermostat and controls are set up per the manufacturer: staging, heat pump settings, blower speeds, and auxiliary heat lockouts where used.
- Leave the numbers with the job. A commissioning record is what protects you on a callback, and it's the baseline for every later service call.
Printable forms: AC start-up and commissioning checklist, static pressure and airflow test sheet, combustion analysis log and the install job completion checklist.
Quick reference
| Check | Pass mark | Source |
|---|---|---|
| Fan airflow | ±15% of design | ENERGY STAR checklist item 3.8 |
| Subcooling (TXV) | ±3°F of manufacturer target | ENERGY STAR checklist item 2.15 |
| Superheat (fixed orifice) | ±5°F of manufacturer target | ENERGY STAR checklist item 2.15 |
| Run time before charge readings | 15 minutes | ENERGY STAR checklist section 2 |
| Furnace firing rate | Within 5% of nameplate | ACCA 5, per ENERGY STAR |
| Room airflow (if balanced) | Greater of ±20% or 25 CFM | ENERGY STAR checklist item 4.2 |
| Duct leakage, new | 10% or less inside, 6% or less outside the envelope | ACCA 5, per ENERGY STAR |
Sources
- ENERGY STAR, National HVAC Commissioning Checklist, Single-Family New Homes (Rev. 14): energystar.gov
- ENERGY STAR, HVAC Quality Installation Sponsor Guide, Version 3: energystar.gov
- ENERGY STAR / ACCA, Intro to ACCA's QA Contractor Program (summary of ACCA 5 QI elements): energystar.gov
- ACCA, Standard 5: HVAC Quality Installation Specification (ANSI/ACCA 5 QI), the standard these documents apply.
Was this guide useful?
One field tip a week
A short, practical HVAC tip in your inbox every week: diagnostics, charging, airflow and code changes. Free, unsubscribe anytime.
We'll only use your email for the newsletter. Privacy policy.
Tools for this job
Superheat & Subcooling Calculator
Enter your line temps and saturation temps; get superheat and subcooling instantly.
TSHTarget Superheat Calculator
Target superheat for piston and cap-tube systems from indoor wet bulb and outdoor dry bulb.
CFMFurnace Airflow from Temperature Rise
Estimate furnace CFM from input BTU, efficiency and the supply/return temperature rise.
Related guides
How to Pull a Deep Vacuum: Micron Targets and the Decay Test
Evacuate a system properly, covering nitrogen pressure test, rig setup, micron targets, and how to read a standing decay test for leaks vs. moisture.
Rooftop Unit Start-Up: Three-Phase Voltage, Compressor Rotation and the Checks That Matter
What to check when you start up a packaged rooftop unit - three-phase voltage imbalance (2% limit) and how to calculate it, scroll compressor rotation, the 208-volt transformer tap, condensate trap, gas pressure testing and the readings to record, following Carrier's rooftop unit instructions.
Residential Duct Design Basics: Friction Rate, Equivalent Length and Velocity Limits
How residential duct sizing works under ACCA Manual D - total effective length, friction rate, the velocity limits for supply and return ducts and grilles, and the flex duct installation rules that keep the design working. Based on the U.S. Department of Energy's Building America guides.
Brazing with a Nitrogen Purge: Why, How Much Flow, and Setup
How to flow nitrogen while brazing refrigerant lines so copper oxide scale doesn't plug TXVs, screens and filter-driers: purge first, then a low flow, core removal, flow rates and the usual mistakes.
Field reference for trained technicians. Always follow the equipment manufacturer's instructions, local code and safe work practices. See our editorial standards, or report a correction.